With budget proposals to cut nearly £3.3m from highway maintenance over the next three years, the state of Carmarthenshire's roads is likely to get worse. As far as the Welsh Government are concerned, the cost to bring back our roads to perfect condition, the 'zero defects backlog value' as it is known, is £17.47m. The council, by comparison, has a probably more realistic figure of £54m.
A recent scrutiny committee looked at the figures presented in a report. Amongst the reasons for this huge difference is that the WG figures were collated in 2009 and used a different method of testing and sampling.
The WG review of backlog figures has been put on hold and the committee wondered whether in fact it "did not wish to acknowledge the true state of the Welsh highway network and its lack of financial support for local authorities sufficient funding". The committee agreed that the WG should be lobbied to restart their review and address the lack of funding for road repairs.
So concerned were the committee with regards to the authority's own budget plans in relation to road defects they decided they needed a seminar in corporate manslaughter. This was agreed and it was also decided that all members would benefit from such a seminar and not just in relation to road conditions....
Coincidentally the RAC published results today from Freedom of Information requests across England and Wales for figures relating to claims made against local authorities for damage to cars from poorly maintained roads. The total bill is around £3.2m. The figures for Wales show that in Carmarthenshire, out of 39 claims made in 2013/14 only one was successful, costing £89.
One reason for the low figure is not that our roads are perfect, far from it (despite the best efforts of the road repair crews, who's numbers will further diminish in the planned cuts), it's that very few drivers actually bother to make an insurance claim against the council for such damage.
The other reason for this low figure, revealed in the scrutiny minutes, is that the current internal code of practice ("vetted by a QC") makes it difficult for motorists to bring claims and the success rate for deflecting all claims so far is currently 75%.
However, Carmarthenshire is not alone with such an approach and across the UK only 23% of all claims were approved.
The RAC suggests that these figures are the tip of the iceberg and central government should think twice about funding projects such as the HS2 scheme whilst the UK road infrastructure crumbles away.
As for the Welsh Government, the plans and feasibility studies for the proposed M4 relief road had cost over £15m by 2009, goodness only knows what the costs have reached now, with still not an inch of tarmac laid.
In Carmarthenshire, with its £54m backlog and £3.3m cuts to highways, the council has just put in several planning applications for 'Gateway displays' on the various highway approaches to Llanelli. These involve ornate stone structures, floral displays and decorative signage. The total cost of the projects, and ongoing maintenance, is unknown but likely to be a considerable sum.
Still at least they'll look nice as we negotiate our way round the worsening potholes....
A recent scrutiny committee looked at the figures presented in a report. Amongst the reasons for this huge difference is that the WG figures were collated in 2009 and used a different method of testing and sampling.
The WG review of backlog figures has been put on hold and the committee wondered whether in fact it "did not wish to acknowledge the true state of the Welsh highway network and its lack of financial support for local authorities sufficient funding". The committee agreed that the WG should be lobbied to restart their review and address the lack of funding for road repairs.
So concerned were the committee with regards to the authority's own budget plans in relation to road defects they decided they needed a seminar in corporate manslaughter. This was agreed and it was also decided that all members would benefit from such a seminar and not just in relation to road conditions....
Coincidentally the RAC published results today from Freedom of Information requests across England and Wales for figures relating to claims made against local authorities for damage to cars from poorly maintained roads. The total bill is around £3.2m. The figures for Wales show that in Carmarthenshire, out of 39 claims made in 2013/14 only one was successful, costing £89.
One reason for the low figure is not that our roads are perfect, far from it (despite the best efforts of the road repair crews, who's numbers will further diminish in the planned cuts), it's that very few drivers actually bother to make an insurance claim against the council for such damage.
The other reason for this low figure, revealed in the scrutiny minutes, is that the current internal code of practice ("vetted by a QC") makes it difficult for motorists to bring claims and the success rate for deflecting all claims so far is currently 75%.
However, Carmarthenshire is not alone with such an approach and across the UK only 23% of all claims were approved.
The RAC suggests that these figures are the tip of the iceberg and central government should think twice about funding projects such as the HS2 scheme whilst the UK road infrastructure crumbles away.
As for the Welsh Government, the plans and feasibility studies for the proposed M4 relief road had cost over £15m by 2009, goodness only knows what the costs have reached now, with still not an inch of tarmac laid.
In Carmarthenshire, with its £54m backlog and £3.3m cuts to highways, the council has just put in several planning applications for 'Gateway displays' on the various highway approaches to Llanelli. These involve ornate stone structures, floral displays and decorative signage. The total cost of the projects, and ongoing maintenance, is unknown but likely to be a considerable sum.
Still at least they'll look nice as we negotiate our way round the worsening potholes....